百能 百能
Focus on global challenges and pressures, provide competitive energy and environmental solutions and services, and continuously create maximum value for customers.
Project Background
The project provides two waste-gas and waste-liquid incineration lines, each rated at 8 t/h. Under normal load they jointly treat 11.364 t/h of continuous waste liquid, 2,372.6 Nm³/h of continuous waste gas and 4.31 t/h of C1 fraction, while accommodating 12,750 Nm³/h of intermittent gas from the upstream ethane-to-alpha-olefins section. Annual design operation is 8,000 hours. The system serves the upstream and downstream ethane-to-alpha-olefins sections, POE unit, laboratory, tank farm and other facilities, reducing and stabilizing hazardous waste. Incinerator ash is solidified and stabilized before hazardous-waste landfill disposal. Flue gas is treated by the downstream ultra-low-emission system before stack discharge. Mature, reliable process arrangements deliver emissions better than GB 18484-2020.

Technical Characteristics

Parallel lines: Each line is rated at 8 t/h and 90 MW. Redundant capacity allows one line to treat all continuous and intermittent gas while the other is under maintenance.

High-calorific-value feed: The theoretical waste-liquid combustion temperature can reach 1,575°C. Membrane water walls with a protective refractory zone withstand high temperature, resist coking and accommodate composition changes.

Low-NOx combustion: Air staging and separated overfire air (SOFA) suppress NOx in the oxygen-deficient primary zone while ensuring burnout. SCR further reduces NOx to below 50 mg/m³.

Dioxin control: Quenching to 200°C within 1 second and activated-carbon injection inhibit dioxin re-formation.

Automation and interlocks: The DCS regulates combustion temperature, negative pressure, feedwater and quench-water flow. Critical interlocks use two-out-of-three redundancy to meet the specified safety-integrity requirements.

Co-treatment: Continuous liquids and gases, C1 fraction and intermittent gases containing hydrocarbons, hydrogen, CO and methane are handled together. Pilot flames stabilize combustion at low load.

Solution

Centralized incineration: Waste liquids, gases and C1 fraction from the process sections, POE unit, laboratory and tank farm are treated together.

Staged firing: Five waste-liquid burners, one waste-gas burner and one C1-fraction burner are installed at the furnace top, with corner overfire air. Steam-atomizing lances produce droplets ≤40 μm for complete combustion without water-wall impingement.

Heat recovery: Membrane-wall waste-heat boilers produce approximately 74 t/h per line of superheated steam at 4.0 MPa and 410°C for the plant network.

Purification train: Incinerator → waste-heat boiler → quench tower → activated carbon/dry acid removal → bag filter → SCR → low-low-temperature economizer → induced-draft fan → stack.

Feed buffering: Acetic-acid, high-temperature, low-temperature and POE waste-liquid tanks, plus underground tanks, accommodate intermittent discharge and maintenance conditions.

Corrosion and insulation: The quench tower is lined with 2205 stainless steel. Insulated external furnace surfaces remain ≤50°C. Electric heating on ducts and hoppers prevents condensation during treatment of chlorine- and sulfur-rich wastes.

Project photograph

Project photograph

Project photograph

Project photograph

Project photograph

Project photograph

Project photograph

Get The Effect

Waste reduction and stabilization: Annual waste-liquid treatment is 90,912 tonnes. The source's results section reports waste-gas flow of 19,003.6 Nm³/h and C1 fraction of 4.31 t/h. Residue loss on ignition is <5%; ash is solidified and landfilled safely. Emission guarantees under GB 18484-2020: particulate matter ≤30 mg/m³, CO ≤100 mg/m³, SO₂ ≤100 mg/m³, NOx ≤150 mg/m³ with capability for enhancement to ≤35 mg/m³, and dioxins ≤0.5 ng-TEQ/m³. Reliability: Design operation is ≥8,000 hours per year and ≥333 continuous days, equipment life is 20 years and operating range is 60–110%. Energy recovery: Both lines at full load produce approximately 148 t/h of superheated steam, reducing purchased steam requirements. Noise and residues: Equipment noise is ≤85 dB(A). Fly ash, spent catalysts and filter bags are managed as hazardous waste to prevent secondary pollution. Safety: Furnace pressure, combustion temperature, quench-water flow and ammonia injection are automatically controlled. Redundant interlocks protect personnel and equipment during abnormal conditions including deflagration, power loss and water loss.
Copyright © 2026 Pyneo Co.,Ltd. All Rights Reserved. 浙ICP备20004608号-2 Sitemap