The 60% three-dimensional model review for the oil-residue gasification filter-cake metal-recovery unit of Shandong Yulong Petrochemical's Phase I refining and petrochemical integration project was recently held at pyneo. Experts agreed that equipment and piping layouts were sound and met safety and operability requirements. Approval moves the unit from the technical scheme toward engineering implementation and supports detailed design, manufacturing, construction and operation.

The Yulong development is identified in the national petrochemical industry planning framework and is a flagship of Shandong's restructuring and replacement of old growth drivers. Phase I investment is approximately RMB 127.4 billion, with 20 million tonnes per year of refining, 3 million tonnes per year of ethylene and advanced chemical-materials units. The metal-recovery facility is central to hazardous-waste treatment, rare-metal recovery and energy reuse.
pyneo's independently developed multiple-hearth incineration process forms part of its complete closed-loop resource-recovery technology. It has already operated continuously and reliably in a comparable 60,000-tonne-per-year Zhejiang Petroleum & Chemical project, providing a proven basis for this installation.

60,000 Tonnes of Filter Cake, Approximately 4,000 Tonnes of Metal-Rich Ash
Oil-residue gasification filter cake contains valuable vanadium, nickel and molybdenum. A lack of economical treatment has long constrained greener refining. The unit is designed for 60,000 tonnes per year of filter cake and approximately 4,000 tonnes of recovered metal-rich ash, together with flue-gas heat recovery and multistage purification.

Dedicated equipment increases metal-ash recovery and optimizes exhaust treatment while reducing operating costs. The process combines harmless treatment, volume reduction, resource recovery and energy recovery to close the refinery's green production loop.
At the review, pyneo presented the process package, flow scheme, equipment and piping arrangement and safe-operation provisions. Experts examined the model against applicable standards and operating experience, focusing on major pipe routes, space utilization and safety. They found equipment selection and layout compliant, pipe routing appropriate and future maintenance and operation adequately considered, meeting the 60% review requirements.
Expected Annual Benefits of Approximately RMB 350 Million
Estimated annual external-disposal savings are RMB 120 million. Direct operating benefits are approximately RMB 230 million, producing comprehensive annual benefits of around RMB 350 million. Rare-metal recovery, deep heat utilization and ultra-low emissions create an internal circular-economy chain, reducing carbon emissions and off-site solid waste and providing a replicable petrochemical solution.
At the time of publication, Phase I was approaching full-process commissioning, with core units completing handover and individual and integrated trials; full-process startup was expected in Q2 2026. The metal-recovery unit now advances into detailed design and manufacturing, with all parties coordinating delivery.

pyneo will continue applying high-temperature thermochemical conversion and resource-recovery technologies to turn waste residue into valuable feedstock and disposal burdens into productive value, contributing to petrochemical upgrading and ecological development.


To be the most satisfactory energy and environment company in the world